Fabrication & Installation of 2 Extension Manifolds for T22/T23 Site including all the Civil & Mechanical Works |
Client: DNO |
Location: Zakho,Tawka Field |
Duration: 2019 - 38 Working Days |
Fabrication & Installation of 3 Manifolds (Wellhead, Perimeter & Extension) for T25N Well including all the related Civil & Mechanical Works |
Client: DNO |
Location: Zakho,Tawka Field |
Duration: 2019 - 42 Working Days |
Fabrication & Installation of 2 Manifolds (Wellhead & Perimeter) for T8 Well including all the related Civil & Mechanical Work |
Client: DNO |
Location: Zakho,Tawka Field |
Duration: 2019 - 35 Working Days |
Mechanical 7 Structural Fabrication & Installation work for the PSK Pumping Station as well as Installation & Alignment of 2 Export Pumps & 2 Transfer Pumps |
Client: DNO |
Location: Zakho,Tawka Field |
Duration: 2019 - 50 Working Days |
Flare Stack Unit Installation and Hook up in T50 and T51 well areas |
Client: DNO |
Location: Zakho,Tawka Field |
Duration: December 2018 to February 2019 (25 Working days) |
Kormala – Kalak 24” Oil Pipeline |
Location: Kormala-Kalak |
Scope of Work:Welding, Tie in, lowering, bending, coating |
Distance: 40Km |
Kalak– Alqosh 36” Oil Pipeline |
Location: Duhok-Iraq |
Scope of Work:Welding, Tie in, lowering, bending, coating |
Distance: 80Km |
Semel – Fishkhabour 36” Oil Pipeline |
Location: Duhok, Zakho – Iraq |
Scope of Work:Welding, Tie in, lowering, bending, coating |
Distance: 41Km |
Bandawa-Kashe Power Plant 36” Gas Pipeline |
Location: Duhok – Iraq |
Scope of Work:Welding, Tie in, lowering, bending, coating |
Distance: 20Km |
Kormala – Alqosh 24” &36” Oil Pipeline |
Location: Erbil-Duhok, Iraq |
Scope of Work:Welding, Tie in, lowering, bending, coating |
Distance: 120Km |
36” Oil Pipeline Hydrostatic test |
Location: Duhok – Iraq |
Scope of Work:36” Oil Pipeline Hydrostatic test |
Distance: 41Km |
36” Oil Pipeline Fiber optic and C.W. |
Location: Semel Fishkhabour |
Scope of Work:36” Oil Pipeline Fiber optic and C.W. |
Distance: 41Km |